Overview
Program Timeline (PDF) Project Phase Descriptions Historical Timeline
Project | Current Status |
---|---|
Grants and Agreements | Live |
Conflict of Interest | Live |
Institutional Review Board (IRB) | Project Start Date: Q1 2025 |
Institutional Animal Care and Use Committee (IACUC) | Project Start Date: Q3 2026 |
Animal Operations
|
Project Start Date: Q1 2027 |
Safety
|
Project Start Date: Q3 2027 |
Questions? Email researchportal@wvu.edu.
Projects in Progress
Grants and Agreements Project
Implementation of the Huron Grants and Agreements module. The project has a proposed timeline of 56 weeks and will engage the campus community throughout the implementation.
-
Onboarding
Onboarding
-
Development Iterations
Development Iteration
-
Test
Test
-
Deploy
Deploy
-
Support
Support
Current Phase: Deploy
Live as of January 13, 2025
During the new system's stabilization period, the Huron team will work to transition all project roles and responsibilities to the Client team.
- Support end users as they transact business using the new system
- Conduct post go-live assessment
- Monitor and tune production environment
- Resolve software bugs and other issues
- Confirm ongoing plan to support and maintain the system
- Provide support to help desk personnel as needed
Conflict of Interest Project
Implementation of the Huron Conflict of Interest module.
-
Onboarding
Onboarding
-
Development Iterations
Development Iteration
-
Test
Test
-
Deploy
Deploy
-
Support
Support
Current Phase: Deploy
Live as of January 13, 2025
During the new system's stabilization period, the Huron team will work to transition all project roles and responsibilities to the Client team.
- Support end users as they transact business using the new system
- Conduct post go-live assessment
- Monitor and tune production environment
- Resolve software bugs and other issues
- Confirm ongoing plan to support and maintain the system
- Provide support to help desk personnel as needed